Construction Work
Current work in progress
January 2026
With the completion of the exterior structure, the interior construction begins. The result will be a highly functional laboratory building offering maximum flexibility and based on a sustainable concept. The further development of office, seminar, and social areas follows the principles of an open, modern workplace that meets the demands of New Work.
Attention: Deliveries to the HIRI site and other construction work on the medical campus may result in debris on traffic routes.
Construction Work Schedule
2025
September 24:Roofing ceremony
2023
December: Construction of the building shell begins
August: Start of excavation of the construction pit and implementation of the shoring
July: Start of construction
April: Preliminary infrastructure works
2022
December: Application for project funding
August: Construction permit
May: Design planning completed
2021
May: Demolition of the former Urology Department at the future HIRI site on the Medical Campus Würzburg
2020
May: Pre-planning completed
2019
July: Leasehold agreement
2018
December: Commissioning DORANTHPOST Architekten, work phase 1 — 8
October: 1st prize: DORANTHPOST Architekten
March: Architectural competition
2017
November: Coordination talks
May: Cooperation agreement with UKW
2016
November: Resolution of the Supervisory Board