Construction Work

Current work in progress

With the completion of the exterior structure, the interior construction begins. The result will be a highly functional laboratory building offering maximum flexibility and based on a sustainable concept. The further development of office, seminar, and social areas follows the principles of an open, modern workplace that meets the demands of New Work.

Attention: Deliveries to the HIRI site and other construction work on the medical campus may result in debris on traffic routes.

 

Construction Work Schedule

2025

September 24:Roofing ceremony

2023

December: Construction of the building shell begins

August: Start of excavation of the construction pit and implementation of the shoring

July: Start of construction

July:Groundbreaking ceremony

April: Preliminary infrastructure works

2022

December: Application for project funding

August: Construction permit

May: Design planning completed

2021

May: Demolition of the former Urology Department at the future HIRI site on the Medical Campus Würzburg

2020

May: Pre-planning completed

2019

July: Leasehold agreement

2018

December: Commissioning DORANTHPOST Architekten, work phase 1 — 8

October: 1st prize: DORANTHPOST Architekten

March: Architectural competition

2017

November: Coordination talks

May: Cooperation agreement with UKW

2016

November: Resolution of the Supervisory Board