Construction Work
With the completion of the exterior structure, the interior construction begins. The result will be a highly functional laboratory building offering maximum flexibility and based on a sustainable concept. The further development of office, seminar, and social areas follows the principles of an open, modern workplace that meets the demands of New Work.
Construction Work Schedule
2025
September 24: Roofing ceremony
2023
December: Construction of the building shell begins
August: Start of excavation of the construction pit and implementation of the shoring
July: Start of construction
July: Groundbreaking ceremony
April: Preliminary infrastructure works
2022
December: Application for project funding
August: Construction permit
May: Design planning completed
2021
May: Demolition of the former Urology Department at the future HIRI site on the Medical Campus Würzburg
2020
May: Pre-planning completed
2019
July: Leasehold agreement
2018
December: Commissioning DORANTHPOST Architekten, work phase 1 — 8
October: 1st prize: DORANTHPOST Architekten
March: Architectural competition
2017
November: Coordination talks
May: Cooperation agreement with UKW
2016
November: Resolution of the Supervisory Board